This page shows you how we run our typical PRINCE2 training course; we adjust the schedule to accommodate special requirements including religious observances, vital meetings or major cultural events.
Day 1
|
Time
|
Activity
| |
9:00
|
Introductions
| |
10:00
|
Business Case
| |
10:30
|
Organisation – Group activities: Objective exam question, Mix n’ match (30 min)
| |
12:00
|
Lunch
| |
13:00
|
Starting Up a Project
| |
14:00
|
Directing a Project
| |
15:00
|
Initiating a Project – Objective exam question (30 min)
| |
16:30
|
Overview of Day – Activity: Create process time-line (15 min).
| |
17:00
|
Finish (trainer available for questions / mentoring)
|
Homework: Crosswords, topic introductions, reading, objective exam question.
Day 2
|
Time
|
Activity
| |
9:00
|
Review of homework/questions answered
| |
9:30
|
Plans – Activities: Odd one out, complete table (10 min)
| |
10:00
|
Planning
| |
10:30
|
Product Based Planning
| |
11:00
|
Managing Product Delivery – Activities: Role play, Mix n’ match (15 min)
| |
11:15
|
Controlling a Stage
| |
12:00
|
Lunch
| |
13:00
|
Managing Stage Boundaries – Activity: Exception Procedure (20 min)
| |
14:00
|
Closing a Project
| |
15:00
|
Management of Risk – Activity: Create a Risk Log entry (15 min)
| |
16:00
|
Controls & Exam technique – Activity: Increase Control on a Project
| |
17:00
|
Finish (trainer available for questions / mentoring)
|
Homework: Crosswords, topic introductions, Sample Foundation exam, objective exam question
Day 3
|
Time
|
Activity
| |
9:00
|
Review of Practise Foundation Exam & objective exam question
| |
9:30
|
Quality in a Project Environment
| |
10:30
|
Quality Review Technique – Activity: Quality Review of a provided product & associated product description (15 min)
| |
11:00
|
Configuration Management
| |
11:30
|
Change Control
| |
11:55
|
Change Control Technique – Activity: Categorise issues (5 min).
| |
12:00
|
Lunch
| |
13:00
|
Sample Foundation exam paper & discussion
| |
15:30
|
Foundation exam paper (75 questions, 60 minutes, closed book)
| |
17:00
|
Finish (trainer available for questions / mentoring)
|
Homework: objective exam questions, Practitioner notes, strategy game background and Mandate.
Day 4
|
Time
|
Activity
| |
9:00
|
Background review, project mandate review schedule review.
| |
9:30
|
Starting up a Project
| |
10:30
|
Initiating a Project
| |
11:30
|
Practitioner question and explanation review
| |
12:30
|
Lunch
| |
13:00
|
Controlling a stage
| |
14:00
|
Closing a Project
| |
15:00
|
Practitioner question and explanation review
| |
17:00
|
Finish (trainer available for questions / mentoring)
|
Homework: objective exam questions and Practitioner notes
Day 5
|
Time
|
Activity
| |
9:00
|
Review of topics covered and objective exam questions
| |
11:00
|
Question and answer session
| |
12:00
|
Lunch
| |
13:30
|
Practitioner exam (9 questions, 3 hours, PRINCE2 manual only)
| |
17:00
|
Finish (usually a social event is organised where everyone can wind down)
|
|
|