1. The Project Board is responsible for one or more aspects of the process Closing a Project.
The Project Manager, in conjunction with Project Support and Project Assurance, is responsible for the process Closing a Project, although Confirming Project Closure (DP5) is carried out by the Project Board. The process description for Closing a Project is found on page 154 of the PRINCE2 Manual.
2. What are some reasons for having a formal end to a project?
There are many advantages to having a clear end to the project. You can find some of these advantages on page 153 of the PRINCE2 Manual.
3. What is the main reason for project files to be secured and archived at the end of the project?
The answer to this question is found on page 158 of the PRINCE2 Manual.
4. What would most likely be the main source of follow-on actions at the end of the project?
A number of actions may be required after the project and they are likely to come mainly from 'pending' Project Issues. Read about this on page 160 of the PRINCE2 Manual.
5. Which of the following statements is true?
One or more post-project reviews are held after project closure to determine if the expected benefits have been obtained. The answer to this question is found on page 161 of the PRINCE2 Manual.
6. Which party is responsible overall for the sub-process Evaluating a Project (CP3)?
The overall responsibility for this sub-process lies with the Project Manager although additional information could come from anyone involved in the project. The answer to this question is found on page 164 of the PRINCE2 Manual.
7. The Business Case provides the basis for the:
Whether a project outcome is successful should need to be assessed against the Business Case for that project. The answer to this question is found on page 200 of the PRINCE2 Manual.
8. Which party is responsible for commissioning and chairing the post-project review?
The Executive has the responsibility of ensuring that the post-project review takes place. You can read more about the responsibilities of the Executive on page 209 of the PRINCE2 Manual.
9. Which of the following statements is true?
The main aim of the post-project review is to review the benefits achieved by the project's products, which is determined after project closure. The answer to this question is found on page 246 of the PRINCE2 Manual.
10. Which of the following statements is true?
While it is not a project activity to produce the post-project review, it is part of the Closing a Project process to plan it. The Project Manager is responsible for this task. The answer to this question is found on page 161 of the PRINCE2 Manual.
11. Which of the following would be the most appropriate option if a viable Business Case does not exist for the project?
A key philosophy of PRINCE2 is that its Business Case must drive the project. It is vital that the Business Case remains viable throughout the project. The answer to this question is found on page 197 of the PRINCE2 Manual.
12. Identifying Follow-on Actions (CP2) prepares a plan for:
Quality reviews should be carried out before the project has finished – during each stage is recommended. Notification of the project closure is carried out by the Project Board in Confirming Project Closure DP5 . The purpose of the Identifying Follow-on Actions (CP2) sub-process is outlined on page 161 of the PRINCE2 Manual.
13. Which of the following is not a feature of the process Closing a Project?
Although useful lessons learned are passed on within Closing a Project there are no further stages so no more can be approved. Features of Closing a Project are found on page 154 of the PRINCE2 Manual.