Overview
The Project Manager must check that progress during a stage is adhering to the Stage Plan and is within the defined Tolerances. This can be done by:
After these are reviewed there are 3 possible outcomes:
- The stage is within Tolerances, leading to CS6 Reporting Highlights and CS1 Authorising a Work Package
- Corrective action is required to remain within Tolerances; proceeded to CS7 Taking Corrective Action
- The stage is expected to go beyond stage or project Tolerances leading to CS7 Taking Corrective Action and CS8 Escalating Project Issues, perhaps creating an Exception Report.
Responsibility for carrying out the review of stage status is bestowed to the Project Manager. This is a process likely to require DP4 Giving ad hoc Direction for ad hoc advice from the Project Board.
Method links
Tips
- This process always creates a management product i.e. either an Exception Report or Highlight Report
- This process is visited many times during a single stage
- The status, at a minimum, should be reviewed weekly in small projects, and fortnightly or monthly in large projects.
- Some elements near the critical path may be measured more frequently due to their importance.