Home > PRINCE2® > CS - Controlling a Stage - Quiz
1. Controlling a Stage describes the day-to-day work of the Project Manager. Which of the following statements is false?
Controlling a Stage is the process that describes the day-to-day work of the Project Manager in handling the project stage. All of Controlling a Stage may be used in an event-driven manner. To read more on the context in which Controlling a Stage is used, see page 96 of the PRINCE2 Manual.
2. Which of the following is not an objective of the process Controlling a Stage?
Identification of the products to be delivered by the project is a key activity of the process Initiating a Project. The objectives of the process Controlling a Stage are found on page 97 of the PRINCE2 Manual.
3. Which of the following is not a key activity of the sub-process Assessing Progress (CS2)?
The Business Case is revised or updated for each End Stage Report with information from the stage that is closing and the next stage's plan, using the process Updating a Business Case (SB3). The key activities of Assessing Progress (CS2) can be found on page 103 of the PRINCE2 Manual.
4. Which of the following statements is true?
Maintaining an accurate and current picture of work progress and status of resources are the main objectives of Assessing Progress (CS2). The answer to this question is found on page 103 of the PRINCE2 Manual.
5. What is the main objective(s) of the sub-process Capturing Project Issues (CS3)?
Capturing Project Issues (CS3) provides the entry point for all external stimuli, such as changes of scope, notification of problems or advice of new risks. All Project Issues should be entered into the Issue Log as soon as they are identified. The answer to this question is found on page 106 of the PRINCE2 Manual.
6. Which would be the most likely first course of action when the Project Manager encounters a Project Issue?
Assessing a Project Issue before making a decision on a course of action is a fundamental principle of the sub-process Examining Project Issues (CS4). The answer to this question is found on page 107 of the PRINCE2 Manual.
7. Confirmation that the Work Package has been completed satisfactorily involves checking that:
The answer to this question is found on page 124 of the PRINCE2 Manual.
8. Which of the following statements is true?
Recent Checkpoint Reports will act as inputs to the next Highlight Report, which is produced by the Project Manager for submission to the Project Board. The Highlight Report is time-driven and sent to the Project Board at a frequency dictated by the Project Board. The answer to this question is found on page 240 of the PRINCE2 Manual.
9. What is the main purpose of the Highlight Report?
The Highlight Report is a report that provides the Project Board with a summary of the stage status. The Project Board should define the content and frequency of the Highlight Report. The answer to this question is found on page 115 of the PRINCE2 Manual. You can also read more about Highlight Report on page 241 of the PRINCE2 Manual.
10. Which of the following statements is true?
The Highlight Report provides the Project Board with summary information about the status of the stage and project, and is produced at the frequency requested by the Project Board. The composition of the Highlight Report is found on page 358 of the PRINCE2 Manual. You can also read more about the sub-process Reporting Highlights (CS6) on page 114 of the PRINCE2 Manual.
11. During which PRINCE2 sub-process would an Exception Report be created?
The answer to this question is found on page 119 of the PRINCE2 Manual.
12. The last sub-process in Controlling a Stage is:
13. Controlling a Stage is known as the process that:
In addition to handling day-to-day management of the project Controlling a Stage drives Managing Product Delivery. The answer to this question is found on page 96 of the PRINCE2 Manual.
14. Regarding the sub-process Reviewing Stage Status (CS5) of Controlling a Stage, which of the following statements is false?
Ensuring that the project is properly initiated by approving a plan to develop the Project Initiation Document is an objective of the Authorising Initiation (DP1) not Controlling a Stage. The objectives of the sub-process Authorising Initiation (DP1) can be found on page 74 of the PRINCE2 Manual.
Category: Quiz