Services
Training
Consulting
Conference
Free resources
Why choose us

Training courses
Search for a course
By type
By location
By profession
Special offers

PRINCE2® resources
Introducing PRINCE2®
How PRINCE2® can help
PRINCE2® FAQs
PRINCE2® Forum
PRINCE2® Resources

Free PRINCE2®
reference card



 Home > PRINCE2® > CS - Controlling a Stage - Quiz

Print

1. Controlling a Stage describes the day-to-day work of the Project Manager. Which of the following statements is false?

Controlling a Stage drives Managing Product Delivery
All of Controlling a Stage is used in a time-driven manner

Controlling a Stage is the process that describes the day-to-day work of the Project Manager in handling the project stage. All of Controlling a Stage may be used in an event-driven manner. To read more on the context in which Controlling a Stage is used, see page 96 of the PRINCE2 Manual.

In Controlling a Stage, the Stage Plan is updated with actuals and progress is checked against the plan
The Project Manager uses the process Controlling a Stage to manage any deviations from Stage or Project Plans.

2. Which of the following is not an objective of the process Controlling a Stage?

Identifying the key products that the project will deliver

Identification of the products to be delivered by the project is a key activity of the process Initiating a Project. The objectives of the process Controlling a Stage are found on page 97 of the PRINCE2 Manual.

Manage any deviations from Stage or Project Plans
Manage on-time delivery of products within agreed tolerances
Ensure that quality is achieved as planned.

3. Which of the following is not a key activity of the sub-process Assessing Progress (CS2)?

Monitoring the work that is being carried out
Monitoring the status of resources
Updating Business Case

The Business Case is revised or updated for each End Stage Report with information from the stage that is closing and the next stage's plan, using the process Updating a Business Case (SB3). The key activities of Assessing Progress (CS2) can be found on page 103 of the PRINCE2 Manual.

Updating the Stage Plans with actuals.

4. Which of the following statements is true?

The sub-process Assessing Progress (CS2) requires the Project Manager to submit Checkpoint Reports to the Executive at pre-determined intervals
The sub-process Assessing Progress (CS2) requires the Project Manager to assess Project Issues for impact and to suggest alternative actions
In the sub-process Assessing Progress (CS2), the Project Manager provides the Product Status Account to the Configuration Librarian
In the sub-process Assessing Progress (CS2), the Project Manager monitors work progress and the status of resources.

Maintaining an accurate and current picture of work progress and status of resources are the main objectives of Assessing Progress (CS2). The answer to this question is found on page 103 of the PRINCE2 Manual.


5. What is the main objective(s) of the sub-process Capturing Project Issues (CS3)?

To capture, log and categorise all Project Issues

Capturing Project Issues (CS3) provides the entry point for all external stimuli, such as changes of scope, notification of problems or advice of new risks. All Project Issues should be entered into the Issue Log as soon as they are identified. The answer to this question is found on page 106 of the PRINCE2 Manual.

To produce the Highlight Report required by the Project Board
To ensure that the stage stays within tolerance
To collate all progress information for reporting to programme management.

6. Which would be the most likely first course of action when the Project Manager encounters a Project Issue?

Call for a meeting with the Project Board
Escalate Project Issues and wait for ad hoc direction from the Project Board
Assess each Project Issue for impact and consider alternative actions

Assessing a Project Issue before making a decision on a course of action is a fundamental principle of the sub-process Examining Project Issues (CS4). The answer to this question is found on page 107 of the PRINCE2 Manual.

Draft an Exception Plan.

7. Confirmation that the Work Package has been completed satisfactorily involves checking that:

  1. Appropriate records have been filed in the quality file?
  2. Products have been transferred to configuration management?
  3. Each completed product carries a Product Description?
  4. Quality Log entries are complete?
1, 2 and 3 only
1, 2 and 4 only

The answer to this question is found on page 124 of the PRINCE2 Manual.

2, 3 and 4 only
All of the above.

8. Which of the following statements is true?

A Highlight Report is an event-driven report on the status of a stage's progress
Highlight Reports are submitted to the Project Manager by the Team Manager
The Project Manager uses Highlight Reports to keep control of project stages
A Highlight Report should contain information about achievements in the current period and those expected in the next period.

Recent Checkpoint Reports will act as inputs to the next Highlight Report, which is produced by the Project Manager for submission to the Project Board. The Highlight Report is time-driven and sent to the Project Board at a frequency dictated by the Project Board. The answer to this question is found on page 240 of the PRINCE2 Manual.


9. What is the main purpose of the Highlight Report?

To allow the Project Manager to take stock of the overall project status
To provide the Project Board with a project status summary to monitor stage and project progress

The Highlight Report is a report that provides the Project Board with a summary of the stage status. The Project Board should define the content and frequency of the Highlight Report. The answer to this question is found on page 115 of the PRINCE2 Manual. You can also read more about Highlight Report on page 241 of the PRINCE2 Manual.

To update a Team Manager and the team on the project's status
To enable the Project Board to match project actuals against the Project Plan.

10. Which of the following statements is true?

The Highlight Report is submitted to the Project Manager by the Team Manager at pre-determined intervals
The Highlight Report details the products completed during the report period

The Highlight Report provides the Project Board with summary information about the status of the stage and project, and is produced at the frequency requested by the Project Board. The composition of the Highlight Report is found on page 358 of the PRINCE2 Manual. You can also read more about the sub-process Reporting Highlights (CS6) on page 114 of the PRINCE2 Manual.

Information for the Highlight Report is mainly derived from the Lessons Learned Log
The Project Board may request a Highlight Report upon submission of an Exception Report by the Project Manager.

11. During which PRINCE2 sub-process would an Exception Report be created?

Examining Project Issues (CS4)
Analysing Risks (PL6)
Escalating Project Issues (CS8)

The answer to this question is found on page 119 of the PRINCE2 Manual.

Giving Ad Hoc Direction (DP4).

12. The last sub-process in Controlling a Stage is:

Receiving a Completed Work Package?

The answer to this question is found on page 124 of the PRINCE2 Manual.

Taking Corrective Action?
Completing a Plan?
Designing a Project Management Team?

13. Controlling a Stage is known as the process that:

Is controlled completely by the Project Board?
Provides information for the Project Board to assess the continued viability of the Project?
Handles day-to-day management of the project?

In addition to handling day-to-day management of the project Controlling a Stage drives Managing Product Delivery. The answer to this question is found on page 96 of the PRINCE2 Manual.

The Team Manager is responsible for?

14. Regarding the sub-process Reviewing Stage Status (CS5) of Controlling a Stage, which of the following statements is false?

CS5 decides whether further Work Packages should be proposed
CS5 decides whether any plan modifications are required
CS5 ensures the project is properly initiated by approving a plan to develop the Project Initiation Document

Ensuring that the project is properly initiated by approving a plan to develop the Project Initiation Document is an objective of the Authorising Initiation (DP1) not Controlling a Stage. The objectives of the sub-process Authorising Initiation (DP1) can be found on page 74 of the PRINCE2 Manual.

CS5 decides whether a Project Issue needs to be escalated.

Your score is 0 / 0
Article Discussion Edit History
crazycolour
FAQs | Contact us | Corporate | Terms of use | Privacy policy | Trademarks