1. Which of these is not a product of the Initiating a Project process?
The blank products created in Initiating a Project are the Quality Log, Issue Log and Lessons Learned Log. The Risk Log is created in the sub-process Preparing a Project Brief (SU4). The answer to this question is found on page 14 of the PRINCE2 Manual.
2. Which process addresses how the quality required will be achieved?
The Initiating a Project process identifies the quality control techniques and procedures to be employed during the conduct of the project. The answer to this question is found on page 48 of the PRINCE2 Manual.
3. Which of the following is not an objective of the process Initiating a Project?
The objectives of Initiating a Project are found on page 49 of the PRINCE2 Manual.
4. Which of the following is not a key input to the sub-process Planning Quality (IP1)?
Key inputs for Planning Quality (IP1) are the Project Brief, quality standards and Project Approach. The project management team structure and job descriptions are also updated in this sub-process. The answer to this question is found on page 52 of the PRINCE2 Manual.
5. When does a project 'officially' start?
It is only with the approval of the Project Board that the project can officially begin. Starting up a Project, although one of the PRINCE2 processes, is actually pre-project preparation. It contains the work that PRINCE2 requires to be done before the project can begin. The answer to this question is found on page 231 of the PRINCE2 Manual.
6. Which of the following is a stable element within the Project Initiation Document?
Variations in time, costs and other factors will always occur in a project. Tolerance is the preset dividing line between differences that are permissible and those that require intervention from a higher authority. The various stable and dynamic elements within the Project Initiation Document are found on page 375 of the PRINCE2 Manual.
7. In which process is the Quality Log created?
The Quality Log records each quality review and is updated with the results and dates of quality checking, forming an audit trail of the quality work done in the project. The answer to this question is found on page 272 of the PRINCE2 Manual.
8. Which of these documents acts as a basis against which the Project Board and Project Manager can assess progress, Project Issues and ongoing viability questions?
The Project Initiation Document is assembled in the sub-process Assembling a Project Initiation Document (IP6) and provides a benchmark for all other management decisions that need to be made during the life of the project. The answer to this question is found on page 375 of the PRINCE2 Manual. You can also read more about the Project Initiation Document on page 65 of the PRINCE2 Manual.
9. Which of the following Project Initiation Document component is not a dynamic element?
The Project Initiation Document is a compilation of documents, some of which are dynamic, the rest stable. A list of these elements is found on page 375 of the PRINCE2 Manual. You can also read more about the Project Initiation Document on page 65 of the PRINCE2 Manual.
10. Which of the following statements is not true?
The Project Plan is a mandatory plan, produced in the sub-process Planning a Project (IP2) using the Planning process. Details of the Project Plan are found on page 381 of the PRINCE2 Manual. You can also read about the Project Plan on page 53 of the PRINCE2 Manual.
11. Which sub-process creates the Risk Log?
The Risk Log should be created as early as possible within Preparing a Project Brief (SU4) to hold any details of key risks, their analysis and chosen actions. The answer to this question is found on page 387 of the PRINCE2 Manual.
12. Which of the following elements are contained within the Project Initiation Document?
The composition of the Project Initiation Document can be found on page 375 of the PRINCE2 Manual.
13. What is the principal document that is produced at the end of Initiating a Project?
The purpose of Initiating a Project is to create the Project Initiation Document, which is a contract of understanding in key aspects of the project between the Project Board and the Project Manager. The answer to this question is found on page 48 of the PRINCE2 Manual.
14. The sub-process Assembling a Project Initiation Document (IP6) only has input from other Initiating a Project (IP) sub-processes.
Appointing a Project Management Team (SU3), Preparing a Project Brief (SU4) and Defining Project Approach (SU5) all provide input into the creation of the Project Initiation Document. The information needs that go into the assembling of the Project Initiation Document is found on page 67 of the PRINCE2 Manual.
15. Initiating a Project is triggered automatically upon completion of:
No project should start or continue without the approval of the Project Board i.e. via Authorising Initiation (DP1). The answer to this question is found on page 48 of the PRINCE2 Manual.
16. There are 3 major filing categories within the PRINCE2 document management system, the quality file and the stage files are two of these. What is the third?
The answer to this question is found on page 421 of the PRINCE2 Manual.
17. Quality is planned in the sub-process Planning Quality (IP1). Which of the following lists all those elements of quality management that determine the implementation of the Quality Plan?
The answer to this question is found on page 266 of the PRINCE2 Manual.