1. Which of these is not a product of the Initiating a Project process?

Issue Log
Quality Log
Lessons Learned Log
Risk Log.

The blank products created in Initiating a Project are the Quality Log, Issue Log and Lessons Learned Log. The Risk Log is created in the sub-process Preparing a Project Brief (SU4). The answer to this question is found on page 14 of the PRINCE2 Manual.


2. Which process addresses how the quality required will be achieved?

Planning
Initiating a Project

The Initiating a Project process identifies the quality control techniques and procedures to be employed during the conduct of the project. The answer to this question is found on page 48 of the PRINCE2 Manual.

Starting up a Project
Directing a Project.

3. Which of the following is not an objective of the process Initiating a Project?

It ensures that all project management authorities are appointed

The objectives of Initiating a Project are found on page 49 of the PRINCE2 Manual.

It encourages the Project Board to take ownership of the project
It provides the benchmark for decision-making processes throughout the project's life
It confirms the existence of an acceptable Business Case justifying the project.

4. Which of the following is not a key input to the sub-process Planning Quality (IP1)?

Project Brief
Identified project risks

Key inputs for Planning Quality (IP1) are the Project Brief, quality standards and Project Approach. The project management team structure and job descriptions are also updated in this sub-process. The answer to this question is found on page 52 of the PRINCE2 Manual.

Quality standards
Project Approach.

5. When does a project 'officially' start?

At Starting up a Project
After Starting up a Project, upon receiving approval from the Project Board

It is only with the approval of the Project Board that the project can officially begin. Starting up a Project, although one of the PRINCE2 processes, is actually pre-project preparation. It contains the work that PRINCE2 requires to be done before the project can begin. The answer to this question is found on page 231 of the PRINCE2 Manual.

Once there is a Project Mandate
Once the Project Initiation Document has been assembled.

6. Which of the following is a stable element within the Project Initiation Document?

Project tolerance

Variations in time, costs and other factors will always occur in a project. Tolerance is the preset dividing line between differences that are permissible and those that require intervention from a higher authority. The various stable and dynamic elements within the Project Initiation Document are found on page 375 of the PRINCE2 Manual.

Business Case
Risk Log
Project Plan.

7. In which process is the Quality Log created?

Starting up a Project
Planning
Controlling a Stage
Initiating a Project.

The Quality Log records each quality review and is updated with the results and dates of quality checking, forming an audit trail of the quality work done in the project. The answer to this question is found on page 272 of the PRINCE2 Manual.


8. Which of these documents acts as a basis against which the Project Board and Project Manager can assess progress, Project Issues and ongoing viability questions?

Issue Log
Lessons Learned Log
Stage Plan
Project Initiation Document.

The Project Initiation Document is assembled in the sub-process Assembling a Project Initiation Document (IP6) and provides a benchmark for all other management decisions that need to be made during the life of the project. The answer to this question is found on page 375 of the PRINCE2 Manual. You can also read more about the Project Initiation Document on page 65 of the PRINCE2 Manual.


9. Which of the following Project Initiation Document component is not a dynamic element?

Project tolerances

The Project Initiation Document is a compilation of documents, some of which are dynamic, the rest stable. A list of these elements is found on page 375 of the PRINCE2 Manual. You can also read more about the Project Initiation Document on page 65 of the PRINCE2 Manual.

Communication Plan
Project Quality Plan
Project organisation structure.

10. Which of the following statements is not true?

The Project Plan may be replaced by a series of Stage Plans in a small-scale project

The Project Plan is a mandatory plan, produced in the sub-process Planning a Project (IP2) using the Planning process. Details of the Project Plan are found on page 381 of the PRINCE2 Manual. You can also read about the Project Plan on page 53 of the PRINCE2 Manual.

The Project Plan provides the Business Case with planned project costs
The Project Plan is used as a baseline against which the Project Board can monitor progress and costs
The Project Plan should be able to support the rest of the Project Initiation Document.

11. Which sub-process creates the Risk Log?

Setting up Project Files (IP5)
Planning Quality (IP1)
Preparing a Project Brief (SU4)

The Risk Log should be created as early as possible within Preparing a Project Brief (SU4) to hold any details of key risks, their analysis and chosen actions. The answer to this question is found on page 387 of the PRINCE2 Manual.

Analysing Risks (PL6).

12. Which of the following elements are contained within the Project Initiation Document?

  1. Communication Plan
  2. Risk Log
  3. Project Approach
  4. Project Mandate.
1, 2 and 3 only

The composition of the Project Initiation Document can be found on page 375 of the PRINCE2 Manual.

1, 2 and 4 only
1, 3 and 4 only
All of the above.

13. What is the principal document that is produced at the end of Initiating a Project?

Project Initiation Document

The purpose of Initiating a Project is to create the Project Initiation Document, which is a contract of understanding in key aspects of the project between the Project Board and the Project Manager. The answer to this question is found on page 48 of the PRINCE2 Manual.

Project Approach
Project Mandate
Risk Log.

14. The sub-process Assembling a Project Initiation Document (IP6) only has input from other Initiating a Project (IP) sub-processes.

True
False.

Appointing a Project Management Team (SU3), Preparing a Project Brief (SU4) and Defining Project Approach (SU5) all provide input into the creation of the Project Initiation Document. The information needs that go into the assembling of the Project Initiation Document is found on page 67 of the PRINCE2 Manual.


15. Initiating a Project is triggered automatically upon completion of:

Planning an Initiation Stage SU6?
Authorising Initiation DP1?

No project should start or continue without the approval of the Project Board i.e. via Authorising Initiation (DP1). The answer to this question is found on page 48 of the PRINCE2 Manual.

Authorising a Stage or Exception Plan DP3?
Designing a Plan (PL1)?

16. There are 3 major filing categories within the PRINCE2 document management system, the quality file and the stage files are two of these. What is the third?

Project file

The answer to this question is found on page 421 of the PRINCE2 Manual.

Specialist file
Management file
The filing cabinet.

17. Quality is planned in the sub-process Planning Quality (IP1). Which of the following lists all those elements of quality management that determine the implementation of the Quality Plan?

System, assurance, control
Log, assurance, reviews, quality management system, system
System, assurance, planning, control

The answer to this question is found on page 266 of the PRINCE2 Manual.

Control, reviews, system.