Services
Training
Consulting
Conference
Free resources
Why choose us

Training courses
Search for a course
By type
By location
By profession
Special offers

PRINCE2® resources
Introducing PRINCE2®
How PRINCE2® can help
PRINCE2® FAQs
PRINCE2® Forum
PRINCE2® Resources

Free PRINCE2®
reference card



 Home > PRINCE2® > SB - Managing Stage Boundaries - Quiz

Print

1. When a stage is forecasted to exceed tolerance, what would be a likely next course of action?

The Team Manager submits an Exception Report to the Project Manager
The Project Manager submits an Exception Report to the Project Board

The Project Manager only has authority to proceed with a stage while it is forecast to remain within tolerance margins. The Exception Report is a document produced by the Project Manager for submission to the Project Board in the event that a stage is forecast to deviate beyond allocated tolerances. The answer to this question is found on page 120 of the PRINCE2 Manual.

The Executive submits an Exception Report to corporate / programme management
The Project Manager submits a Highlight Report to the Project Board.

2. In this process the Project Manager provides information to the Project Board to assess the continuing viability of the project:

Managing Stage Boundaries?

This is one of the objectives of the Managing Stage Boundaries process. Other objectives of the Managing Stage Boundaries process are found on page 138 of the PRINCE2 Manual.

Controlling a Stage?
Managing Product Delivery?
Directing a Project?

3. At which point is the organisation structure of a stage specified?

Before the end of its previous stage

The organisation structure of a stage is specified in the Managing Stage Boundaries process, which takes place before the end of the previous stage. The answer to this question is found on page 140 of the PRINCE2 Manual.

At the end of the starting up phase of the project
At the initiation stage of the project
Once the Project Board has been appointed.

4. When should the Lessons Learned Log be filled in?

At the end of the project
At least at the end of each stage of the project

A note should be made in the Lessons Learned Log throughout the project whenever a good or bad point arises. However, minimally it should be updated at the end of a stage. Refer to page 361 of the PRINCE2 Manual for the outline and purpose of the Lessons Learned Log.

Only at the end of each stage of the project
Whenever the Project Manager has to submit a Highlight Report to the Project Board.

5. When is a stage deemed to be in exception?

When the Project Board feels that the project is not going right
As soon as the stage goes beyond delegated tolerances
As soon as the stage is forecast to go beyond the delegated tolerances

The answer to this question is found on page 150 of the PRINCE2 Manual.

When the Project Manager proposes corrective actions.

6. What activity takes place during an exception assessment?

The Project Board requests an Exception Report from the Project Manager
The Project Manager assesses the project status and decides whether an Exception Report should be submitted to the Project Board
The Project Manager escalates a Project Issue to the Project Board
The Exception Plan is presented to the Project Board.

A forecast deviation beyond tolerance, once recognised, is brought to the attention of the Project Board through an Exception Report. The Project Board may then request an Exception Plan from the Project Manager. The Exception Plan is presented to the Project Board at an exception assessment. The answer to this question is found on page 150 of the PRINCE2 Manual.


7. What is the span of the Exception Plan that replaces the original plan?

The Exception Plan always covers the entire project, from the project start-up to the end of the project
The Exception Plan always runs from the present time to the end of the plan that it replaces

The Exception Plan has the same structure as other PRINCE2 plans (i.e. an Exception Plan for a stage will have the same structure as a Stage Plan). The answer to this question is found on page 151 of the PRINCE2 Manual.

The Exception Plan always runs from the present time to the end of the project
The Exception Plan never spans more than a single stage of the project.

8. Which of the following statements is not true?

An Exception Plan may replace a Stage Plan, a Team Plan or the Project Plan
An Exception Plan replacing a Team Plan does not require the approval of the Project Board
An Exception Plan covers the present plan actuals to the end of the same plan
An Exception Plan is usually not as detailed as the plan that it replaces.

An Exception Plan contains the same level of detail as the plan it replaces. The answer to this question is found on page 225 of the PRINCE2 Manual.


9. Which of the following statements is not true?

The end stage assessment reviews the tolerances set for the next stage
The end stage assessment is not mandatory but when implemented, takes place at the end of a stage

The end stage assessment is a mandatory control point at the end of each stage of a project. It is a point of approval of the work to date and allows the project to progress to the next stage. You can read more about end stage assessment on page 242 of the PRINCE2 Manual.

The end stage assessment reviews the result of the stage against the Stage Plan
The end stage assessment approves the work to date and provides authority to proceed to the next stage of the project.

10. Which parties are typically involved in an exception assessment?

Project Manager and Executive
Project Board members
Project Board and Programme Executive
Project Board and Project Manager.

The purpose of the exception assessment is for the Project Manager to present an Exception Plan to the Project Board. In the case where any of the Project Board's assurance responsibilities have been delegated, the people to whom assurance has been delegated would also participate. The answer to this question is found on page 243 of the PRINCE2 Manual.


11. Every PRINCE2 project should consist of at least how many stage(s)?

Four
Three
One
Two.

Every PRINCE2 project should consist of at least two stages, the initiation stage being mandatory. The answer to this question is found on page 247 of the PRINCE2 Manual.


12. Technical stages are typified by:

The use of a particular set of specialist skills?

Technical stages are different from management stages, which are typified by the commitment of resources and authority to spend. You can read more about technical and management stages on page 248 of the PRINCE2 Manual.

The commitment of resources?
The amount of time required to produced a Work Package?
The number of management stages in the project?

13. Which of the following management products is not re-visited for changes in the PRINCE2 process Managing Stage Boundaries:

Project Quality Plan?
Project Approach?
Project Mandate?

The Project Mandate is a product that is used to trigger Starting up a Project. It is used to create the Project Brief; it does not exist beyond Starting up a Project. page 37 of the PRINCE2 Manual details the transformation of the Project Mandate into the Project Brief.

Project Plan?

14. In the following statements about Managing Stage Boundaries, which is not false?

In Planning a Stage (SB1) the Stage Plan should only include specialist products
The management structure has to be specified in the Stage Plan

This question, in a roundabout way, asks for which is the true statement (the old double-negative). The only true statement here is that the management structure must be specified in the Stage Plan. The answer to this question is found on page 140 of the PRINCE2 Manual.

Quality activities should not appear in the plan
The Risk Log is not updated in this process.

15. Which of the following statements is/are objective(s) of Managing Stage Boundaries?

Assure the Project Board that all products in the current Stage Plan have been completed as defined
Provide the information needed for the Project Board to assess the continuing viability of the Project
Obtain authorisation for the start of the next stage, together with its delegated tolerance margins
All of the above.

All these points are objectives of Managing Stage Boundaries. The answer to this question is found on page 138 of the PRINCE2 Manual.


Your score is 0 / 0
Article Discussion Edit History
crazycolour
FAQs | Contact us | Corporate | Terms of use | Privacy policy | Trademarks